
Well, that situation occurred at the IC hearings in September, and the IC said the lease provision was a matter between private parties. It said the proper venue for the dispute was the courts and not the IC, which ha

As such, wasn’t the IC ignoring the practical effects of its order and the correlative rights of the MO who bargained for the restrictive pooling provision with the OC? In other words, by granting the order, the IC gave authority to the OC to drill a horizontal well across the 1280, and assuming the horizontal wellbore transverses both sections and is commercial, exactly how can a 640 acre spacing unit ever be created at a later time in such a situation? The answer is that it can’t, unless in the unlikely event the OC plugs back the lateral so that it does not extend beyond the hardline boundary for a 640 acre unit that contains the well site (and such a plug back order by the IC would inevitably lead to waste), or the IC deems the east or west halves of the two sections a 640 acre unit in the event the wellbore stays exclusively in the either half. However, I’m unaware that the IC has ever created a 640 acre spacing unit after a well was drilled on a 1280 drilling unit that was created for a single lateral.
Consequently, unless some bizarre series of events later occurred, the granting of the 1280 acre drilling unit effectively created a 1280 spacing unit. Thus, in a practical sense, the only stage in the regulatory process that the lease provision could prevent the creation of a 1280 spacing unit was at the initial hearing for the drilling unit.
So, it seems the only option for the MO after such an order is entered is to obtain an injunction to prevent the drilling of the well until the validity and effect of the lease provision can be determined by the courts. Now it should be noted that neither party may have standing, i.e., an actual “case or controversy,” to have a court hear the issue until after the IC issues an order either granting or denying the request for a 1280. But at bottom, the real and practical issue in this situation is whether the MO or the OC should have the burden of invoking a court’s review.
The IC could have found that the MO had an apparently valid lease provision (obviously an open question, although easily researched) that would be violated if it granted the OC’s request because a well transversing two sections cannot later be made into a 640 acre spacing unit, and accordingly, that it would deny the request because otherwise the correlative rights of the MO would be adversely affected. Then the OC, who is arguably attempting to breach a lease provision, would have the burden of going to court if it still wanted the 1280, instead of the MO having to go to court to rescind it after it already has been created.
My reading of this decision is that the IC is stating that it is the job of the courts to protect the correlative rights of the MO in this situation, rather than the job of the IC, although one of the primary duties of the IC’s O&G Division is to protect the correlative rights of all owners while regulating oil and gas development.
As it stands now, it appears that the MO must present evidence at the drilling unit hearing that the 1280 is not feasible on grounds independent of a contrary lease provision (geologic, economic reasons) in order to possibly prevent the creation of a 1280. In addition, shouldn’t the burden of proof be just a tab bit higher for the party seeking an exception to the rules, i.e., that the requesting party have a little higher burden in overcoming any objections to such a request in order to prevail? After all, there is a reason it is called an exception.
If the MO doesn’t seek an injunction and the well is drilled and later spaced at 1280, what damages does the MO have to prove in court? Well, that would be tricky, as the MO would have to present evidence of some difference in the amount of royalties between a 640 and the 1280. It’s likely that the breach of such a lease provision would be deemed a breach of a covenant and not a condition of the lease, the latter being a basis for terminating the lease, and the former being a basis for only collecting damages that resulted from the breach.
An even tricker situation is presented when there are multiple working interest owners in the proposed unit, and the OC that agreed to the restrictive pooling clause is not the same OC as is requesting the creation of the 1280. Does this “secondary” OC have any duty to abide by, or have its rights limited by, the terms of an agreement to which it wasn’t a party? Too many issues are raised there to be addressed here.
Now, it should be noted that the case last month involved special circumstances. The southern sections in the standup units to be created, which didn’t have the restrictive lease clauses, were entirely under the waters of Lake Sakajawea and over a half mile from shore. The northern sections that had the lease restrictions, however, had some terra firma available. Therefore, the only practical way to reach the offshore sections was to drill a long lateral through the sections that had the lease clause. Although that case involved peculiar circumstances, it doesn’t mean that the IC’s determination would have been any different in a "normal" case, since the legal principles involved are the same.
In any event, the apparent violation of a lease provision should be a factor that the IC considers when determining the size of a drilling or spacing unit, especially when the violation adversely effects a party’s correlative rights. Apparently the IC feels it shouldn’t be a factor.
I have yet to see any persuasive evidence that a single long lateral adequately drains the entire width of a 1280 acre unit. Some companies are saying they need a 1280 for a single well because such a well drains the entire unit, but then say, but hey, if it’s a good well, we will drill another well on the unit. And for some reason the IC buys it. There is only one thing here that we know for sure - - there will be one well on the unit. So therefore, why doesn’t the IC start with the premise that there will be only one well and create a 640, and then a create a second 640 when and if a second well is planned.
I find it especially ironic that the IC doesn’t want to get involved in private lease matters regarding a restrictive pooling clause, and yet everyone knows the unspoken motive for the 1280 requests is so the companies can tie up a lot of leases by drilling a single well. Doesn’t the IC consider it to be getting involved in private lease matters when it creates larger units than necessary and thus allows leases to be held by production when they should otherwise expire if a second well isn’t drilled?